You will not be asked to engineer a backyard to municipal standard. It is still the most useful yardstick available, because it is the city stating in writing what it thinks this ground requires.
Cottonwood Heights maintains 89 miles of storm drain pipe and channel between 4 and 84 inches, 1,620 structures and 104 outfalls into Big Cottonwood Creek, Little Cottonwood Creek and the East Jordan Canal. Section 17.04.020 designs the intermediate parts of that system to a ten-year frequency flood. Where a development has to detain water, section 17.04.070 — amended by ordinance 395 in April 2023 — caps the release rate at 0.2 cubic feet per second per developed acre, and at 0.1 inside a sensitive lands overlay zone.
The sensitive lands chapter, 19.72, is stricter still, and by its own terms applies to all lands located in the city. Stormwater facilities must be built first, before anything else on the site, and must detain the 100-year storm while discharging no more than 0.1 cubic feet per second per acre. Existing natural drainage channels have to remain where they historically are. Where a channel is needed, the code asks for wide shallow swales lined with vegetation or rock instead of narrow deep ditches. Impervious coverage is capped at 30 per cent of any part of a project where a slope stability hazard is present, and beyond that on-site retention is required.
The same chapter is where the wall limits live, and they are tighter than Draper's. No development at all — including grading, retaining walls and structures — on slopes over 30 per cent, save for a narrow exception; and where that exception applies, a slope retaining structure is capped at four feet, with terraced walls limited to twelve feet combined. If your lot climbs hard toward the canyon, that is the number that shapes the design.
All of it is paid for by a monthly stormwater fee, set at $8.69 per equivalent residential unit for 2026-27 on the city's fee schedule and rising three per cent a year. One ERU is 4,000 square feet of impervious surface, which the city defines to include concrete, patios, sports courts, parking lots and rooftops. Whether a specific patio changes a specific bill is a question for the city's stormwater fee policy manual and its fee waiver process, not for us — but it is worth asking before you add a large one, and worth knowing that a grading permit here is charged at 100 per cent of the IBC schedule.